Current Progress of the Mumbai-Ahmedabad High-Speed Rail Corridor 2025

Current Progress of the Mumbai-Ahmedabad High-Speed Rail Corridor 2025

July 23, 2025
GST Reforms May Lead to ₹3,700 Crore Revenue Loss, Says SBI Report

GST Reforms May Lead to ₹3,700 Crore Revenue Loss, Says SBI Report

September 6, 2025
Canada's Admission: Khalistani Terror Groups Funded from Within Its Borders 10 Sep

Canada’s Admission: Khalistani Terror Groups Funded from Within Its Borders 10 Sep

September 6, 2025
Indians Celebrate La Tomatina in Spain with a Bollywood Extravaganza 2025

Indians Celebrate La Tomatina in Spain with a Bollywood Extravaganza 2025

September 6, 2025
Patna Man Behind ‘400 kg RDX’ Threat to Mumbai Police Arrested in Noida

Patna Man Behind ‘400 kg RDX’ Threat to Mumbai Police Arrested in Noida

September 6, 2025
PM Modi to Skip UN General Assembly 2025; S. Jaishankar Likely to Represent India

PM Modi to Skip UN General Assembly 2025; S. Jaishankar Likely to Represent India

September 6, 2025
Citizens’ Relief First, Revenue Second: FM Sitharaman Emphasizes Tax Relief Focus 5 Sep

Citizens’ Relief First, Revenue Second: FM Sitharaman Emphasizes Tax Relief Focus 5 Sep

September 5, 2025
NIRF 2025 MBA Rankings: IIM Ahmedabad Tops, IIT-Delhi Among Top 10 – Full List & Insights”

NIRF 2025 MBA Rankings: IIM Ahmedabad Tops, IIT-Delhi Among Top 10 – Full List & Insights”

September 5, 2025
Putin Warns: Western Troops in Ukraine Would Be ‘Legitimate Targets’—Implications for Peacekeeping 2025

Putin Warns: Western Troops in Ukraine Would Be ‘Legitimate Targets’—Implications for Peacekeeping 2025

September 5, 2025
NIRF Rankings 2025: IIT Patna Shines as Only Bihar Institute in Overall List

NIRF Rankings 2025: IIT Patna Shines as Only Bihar Institute in Overall List

September 5, 2025
Mumbai on High Alert: ‘34 Human Bombs, 400 kg RDX Could Kill One Crore’ – Threat via WhatsApp

Mumbai on High Alert: ‘34 Human Bombs, 400 kg RDX Could Kill One Crore’ – Threat via WhatsApp

September 5, 2025
Shilpa Shetty Calls It “The End of an Era” as Iconic Bastian Bandra Closes Amid ₹60 Crore Fraud Allegations 2025

Shilpa Shetty Calls It “The End of an Era” as Iconic Bastian Bandra Closes Amid ₹60 Crore Fraud Allegations 2025

September 4, 2025
Sheena Bora Case Timeline: From Disappearance to Trial – Indrani & Peter Mukerjea 2025

Sheena Bora Case Timeline: From Disappearance to Trial – Indrani & Peter Mukerjea 2025

September 4, 2025
  • Astrology News
  • Business News
  • Cricket News
  • Education News
  • Entertainment News
  • Fashion News
  • India News
  • Lifestyle News
  • Science News
  • Sports News
  • Startup News
  • Technology News
  • Trending News
  • World News
Sunday, September 7, 2025
  • Login
  • Register
LocalTak
  • Home
  • My account
  • Categories
    • Astrology News
    • Business News
    • Cricket News
    • Education News
    • Entertainment News
    • Fashion News
    • India News
    • Lifestyle News
    • Science News
    • Sports News
    • Startup News
    • Technology News
    • World News
  • Advertise
  • Liberty Wire
No Result
View All Result
LocalTak
No Result
View All Result
Home Travel News

Current Progress of the Mumbai-Ahmedabad High-Speed Rail Corridor 2025

by Satya
July 23, 2025
in Travel News, Business News, India News, Local News, Trending News
251 2
0
Current Progress of the Mumbai-Ahmedabad High-Speed Rail Corridor 2025

Current Progress of the Mumbai-Ahmedabad High-Speed Rail Corridor 2025

492
SHARES
1.4k
VIEWS

Latest update on Mumbai–Ahmedabad Bullet Train corridor: 48% progress, 300 km viaduct done, tunnel breakthrough, electrification started & stations under construction.

Mumbai–Ahmedabad Bullet Train Project: Progress & Key Updates (July 2025)

The Mumbai–Ahmedabad High-Speed Rail Corridor—often dubbed India’s first bullet train—is moving forward at a brisk pace, with major construction milestones achieved and key systems planning entering its final phases.

Construction Progress & Financials

As of March 2025, the project has surpassed the 48 % physical completion mark, with nearly ₹71,000 crore expended on the ₹1.08 lakh crore initiative. All civil contracts across both Gujarat and Maharashtra have been finalised and awarded, and land acquisition along the 508 km corridor is fully complete.

Viaducts, Bridges & Stations

Significant structural work is advancing rapidly:

  • Over 300 km of viaducts have been erected, using efficient full‑span launching methods that accelerate pace tenfold—the project has installed more than 6,455 full‑span units and 925 additional spans.
  • In Gujarat, 16 out of 24 planned river bridges are now complete, with eight more under construction.
  • Of the 12 stations along the corridor, five are fully finished, and three more are in the final stage of construction.
  • The BKC station in Mumbai is shaping into an engineering marvel: located 32.5 metres underground, its foundation is being designed to support a 95 m‑high structure above .

Underground & Tunnel Works

A pivotal section of the project—the 21 km underground tunnel between BKC and Shilphata, including a 7 km stretch under Thane Creek—has seen substantial breakthroughs:

  • On July 10, 2025, the first 2.7 km continuous tunnel was completed, representing a major achievement in the subterranean segment.
  • Work continues on the remaining segment using the New Austrian Tunnelling Method (NATM). An intermediate launch shaft has enabled dual‑end excavation; around 1.6 km has already been excavated from the Shilphata side.
  • In parallel, three massive TBMs (tunnel‑boring machines)—including one with a 13.56 m diameter head—remain stuck at a Chinese port due to clearance delays, affecting the timeline for fully unleashing the tunnelling machines. NHSRCL insists the overall schedule remains unchanged for now.

Track Laying & Systems Work

Track installation is proceeding systematically:

  • In Maharashtra, Larsen & Toubro has emerged as the lowest bidder for the final track‑installation package (T‑1), covering nearly 156.6 km from BKC to the Zaroli border.
  • On the Gujarat side, packages T‑2 and T‑3 are already underway, handled by IRCON and L&T respectively.

Electrical systems and depots are progressing as well. The three depot locations in Thane, Surat, and Sabarmati are advancing through civil and systems work; electrification across the corridor is on schedule.

Trainsets & Timeline

Technology coordination with Japan is in focus:

  • India will deploy Japanese E5 Shinkansen sets for initial trial runs, followed by E10 generation trains for full commercial operations. The E10 trains are scheduled for simultaneous launches in India and Japan around 2030.
  • Indian-built prototypes, made through Make‑in‑India partners like ICF and BEML, are planned for delivery by late 2026 and will help customize trainsets for Indian conditions.

Initial trial operations are expected to begin on a 50 km stretch between Surat and Bilimora around 2026, with commercial services in Gujarat by late 2028, before full corridor service across Maharashtra by 2030.

Governance & Oversight

A parliamentary standing committee has flagged potential challenges—particularly related to cost overruns, supply chain bottlenecks, and limited domestic manufacturing—and has recommended enhanced oversight, local production under Make‑in‑India, and stakeholder coordination to ensure timely delivery.


ComponentStatus (July 2025)
Overall physical progress~48–50% complete
Viaducts300+ km erected; foundation & pier work mostly done
River bridges (Gujarat)16 of 24 finished
Underground tunnel (BKC–Shilphata)First 2.7 km breakthrough; NATM underway
Station construction5 complete; 3 nearing finish
Track installationGujarat work active; Maharashtra T‑1 contract awarded
Trial runs & opening2026 (Surat–Bilimora), Gujarat operations 2028, full corridor 2030
TrainsetsE5 (trial), E10 (commercial from 2030); Indian prototypes by 2026

The Mumbai–Ahmedabad bullet train project remains ambitious but firmly on track, with several engineering milestones achieved in mid‑2025, swift progress on viaduct and station works, and systematic planning for trainsets and operations. Remaining challenges include tunnel‑boring equipment delays and ensuring all systems sync across states—but with focused oversight and international collaboration, India appears set to meet its high‑speed rail vision.

READ ALSO…Jagdeep Dhankhar Paid Surprise Visit to Rashtrapati Bhavan Before Sudden Resignation: Report 23 May

Table of Contents

  • Mumbai–Ahmedabad Bullet Train Project: Progress & Key Updates (July 2025)
    • Construction Progress & Financials
    • Viaducts, Bridges & Stations
    • Underground & Tunnel Works
    • Track Laying & Systems Work
    • Trainsets & Timeline
    • Governance & Oversight
Tags: breakingnewsIndiaNewslatestnewsMumbaiNewstrendingnews
SendTweet123Share
Satya<span class="bp-verified-badge"></span>

Satya

  • Trending
  • Comments
  • Latest
budget

Budget 2025: No Income Tax for Earnings Up to ₹12 Lakh

February 8, 2025
Ranveer Allahbadia: Mumbai Police visit YouTuber Ranveer Allahbadia's home over remarks on ‘India’s Got Latent 2025

Ranveer Allahbadia: Mumbai Police visit YouTuber Ranveer Allahbadia’s home over remarks on ‘India’s Got Latent 2025

February 11, 2025

The Ultimate Guide to Craigslist: Everything You Need to Know Mind-Blowing 2024

February 6, 2025
Cricket-Playing Babas at Mahakumbh Mela 2025 Go Viral in New Video

Cricket-Playing Babas at Mahakumbh Mela 2025 Go Viral in New Video

2
Thandel Box Office Day 1 Collection: Naga Chaitanya and Sai Pallavi's Romantic Thriller Starts Strong

Thandel Box Office Day 1 Collection: Naga Chaitanya and Sai Pallavi’s Romantic Thriller Starts Strong

2
Ranveer Allahbadia Faces Backlash for Inappropriate Jokes on Samay Raina's Show; Neelesh Misra Criticizes ‘Perverted Creators’

Ranveer Allahbadia Faces Backlash for Inappropriate Jokes on Samay Raina’s Show; Neelesh Misra Criticizes ‘Perverted Creators’

2
GST Reforms May Lead to ₹3,700 Crore Revenue Loss, Says SBI Report

GST Reforms May Lead to ₹3,700 Crore Revenue Loss, Says SBI Report

September 6, 2025
Canada's Admission: Khalistani Terror Groups Funded from Within Its Borders 10 Sep

Canada’s Admission: Khalistani Terror Groups Funded from Within Its Borders 10 Sep

September 6, 2025
Indians Celebrate La Tomatina in Spain with a Bollywood Extravaganza 2025

Indians Celebrate La Tomatina in Spain with a Bollywood Extravaganza 2025

September 6, 2025
LocalTak

Copyright © 2017-2025 | All Rights Reserved by LocalTak.
Owned by ASHASWEB PRIVATE LIMITED

Navigate Site

  • About
  • Advertise
  • Privacy & Policy
  • Contact

Follow Us

Welcome Back!

Login to your account below

Forgotten Password? Sign Up

Create New Account!

Fill the forms bellow to register

All fields are required. Log In

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Add New Playlist

No Result
View All Result
  • Home
  • My account
  • Categories
    • Astrology News
    • Business News
    • Cricket News
    • Education News
    • Entertainment News
    • Fashion News
    • India News
    • Lifestyle News
    • Science News
    • Sports News
    • Startup News
    • Technology News
    • World News
  • Advertise
  • Liberty Wire

Copyright © 2017-2025 | All Rights Reserved by LocalTak.
Owned by ASHASWEB PRIVATE LIMITED